On 21 September 2026 the European Commission adopted a mandatory rating scheme for data centers, with separate A-to-G grades for energy and water. A summary as of 3 November 2026, with sources. General information, not legal advice.

Article · Reviewed 3 November 2026

Who it covers

Data centers with an IT power demand of at least 500 kW, which already report to the European database under Delegated Regulation (EU) 2024/1364 (DLA Piper, 9 September 2024). Data centers under construction submit expected values.

The grades

EU rating scheme thresholds at each end of the scale
GradeEnergy (PUE)Water (WUE)
A1.15 or less0.1 or less
GAbove 1.9Above 1.0

Energy and water receive separate grades. The scheme also considers energy sourcing, grid flexibility, whether a site is ready to reuse waste heat, and cooling degree days (Latham & Watkins, 25 September 2026; European Commission, rating scheme act C(2026) 3472).

Energy sourcing, counted strictly

For energy sourcing, "new" clean generation means plants built or substantially refurbished within 10 years, with guarantees of origin from the same bidding zone or Member State, matched to the consumption period (Freshfields, 24 September 2026, updated 8 October 2026).

Key dates

EU rating scheme timeline
DateStep
21 September 2026Commission adopts the rating scheme
21 September to 14 December 2026Consultation on minimum performance standards
21 January 2027Deadline for objections, after Parliament extended its scrutiny on 6 October 2026
Second quarter of 2027Legislative proposal on minimum performance standards expected
15 August 2027First labels due, then every year

Sources: Latham & Watkins, 25 September 2026; Freshfields, 24 September 2026, updated 8 October 2026.

What it means for measurement

The energy grade rests on PUE, which the Joule Ledger reports as the Overhead Ratio at M4 over M3, from at least 12 months of energy data. The water grade needs water metering, which the Joule Ledger does not cover. See the crosswalk.

Questions

Does the scheme apply to small server rooms?

It applies to data centers with an IT power demand of at least 500 kW.

Is the scheme final?

It was adopted by the Commission on 21 September 2026 and is subject to Parliament and Council scrutiny until 21 January 2027.

Sources

  1. DLA Piper, 9 September 2024
  2. Latham & Watkins, 25 September 2026
  3. European Commission, rating scheme act C(2026) 3472
  4. Freshfields, 24 September 2026, updated 8 October 2026

Keep reading

Talk to us.

The EU data-center rating scheme adopted 21 September 2026: separate A-to-G grades for energy (PUE) and water (WUE), who it covers, and the 2027 dates.